Project Track Record

Project PMD Type Percentage Completion (Time)
%
Date of Commencement (MM/DD/YY) Expected Date of Completion (MM/DD/YY) Client Contract Value (Rs.)
Piling Works for Major Bridges Construction Project of the National Road Network (Package 02) –  B-16 Mannar  Bridge Project PMD II Piling 100.00% 5/1/2017 8/10/2017 RDA          28,000,000.00
Senok Automobile (pvt) Ltd PMD II Piling 100.00% 6/30/2017 9/5/2017 Senok Automobile (Pvt) Ltd.          47,000,000.00
Piling work of Senok Head office tower, Colombo 05 PMD II Piling 100.00% 5/10/2017 8/10/2017 Senok trade combine (pvt) Ltd          85,000,000.00
Construction of Proposed Ring Road along West Bank of West Beira Lake PMD I Road 100.00% 5/15/2017 2/20/2018 Colombo Municipal Council       418,069,441.42
Building No. 4 of Waterfront Project PMD III Building 38.23% 6/5/2017 4/24/2019 Hyundai Keangnam Nawaloka Joint Venture (HKN JV)       672,861,824.16
Dialog OFN Backbone Network – Phase VI PMD II Telecom. 100.00% 6/9/2017 11/30/2017 Dialog Broadband Networks (Pvt.) Ltd.       317,940,000.00
Deduruoya Water Supply Project – contract 1 PMD III Water 46.72% 6/12/2017 12/12/2018 NWSDB       647,000,000.00
Deduruoya Water Supply Project – contract 2 PMD III Water 46.72% 6/12/2017 12/12/2018 NWSDB    1,615,000,000.00
Piling Work for Havelock City PMD II Piling 98.02% 6/21/2017 2/28/2018 Havelock City (pvt) Ltd    1,242,000,000.00
Guide wall  construction PMD II D-Wall 91.14% 6/21/2017 3/19/2018 Havelock City (pvt) Ltd       490,000,000.00
Stabilization Of Cuts Slopes at Nugagahapura Below CMC Land using Soil Nailing Technique – Phase 2 PMD II Slope Stabilization 75.87% 7/21/2017 5/3/2018 Colombo Municipal Council (CMC)          61,030,000.00
Piling  & Diaphragm wall Works at Odel Commercial complex , Colombo -07 PMD II Piling 49.33% 8/24/2017 8/30/2018 ODEL PLC       570,000,000.00

 